Ohio BigWind NOT working x years?

Screen Shot 2018-10-12 at 10.08.36 AM

Say it isn’t so! How can this be? Read through this nightmare for a small Ohio community and you will see that a 2nd turbine has also not produced what was expected (promised) by BigWind. Lawsuits are pending.  How many of you live in a community that is flush with cash to be able to afford these lawsuits?? This news is devastating for the local community and our taxpayers. Lawsuits are expensive. Don’t let this happen to you…Have you contacted your legislators and told them how you feel about BigWind invading your community?….

The city of Conneaut has prepared a complaint to be filed in Ashtabula County Common Pleas Court aimed at a long-damaged wind turbine at the city’s lakefront…

The city names three defendants in the complaint: Conneaut City Wind LLC, in care of statutory agent CT Corporation System of New York City; NexGen Energy Partners LLC of Boulder, Colorado; and NexGen’s statutory agent, Matthew O’Conneaut, of Cleveland…

In the complaint, the city alleges the defendants have not made repairs to the turbine, which has been idle since February 2017, when a lightning strike blew off one of three blades and damaged the machine’s internal workings…

The 400-kilowatt turbine was the result of a January 2010 contract between the city and CCW to provide electric power to the sewage plant. The turbine, erected a short time later, provided about 20 percent of the electricity used at the plant. Direct Energy, the primary power supplier, is filling the void, officials have said.

Last year, NexGen told the city it wanted to stretch the contract to 2030 to help it recoup the estimated $250,000 repair cost, officials said at that time. The contract included slight kilowatt-per-hour increases into the contract years, administrators said.

In 2016, the last full year of the turbine’s operation, NexGen charged the city $59,000 for the electricity it produced. The city is charged only when the turbine is producing power, officials have said…

“(Defendants) Conneaut City Wind and NexGen have refused to repair, remove or otherwise restore the ability to of the turbine to generate electricity,” according to the lawsuit…

A larger turbine at Conneaut Middle School, erected by NexGen at about the same time in 2010, never performed as expected. NexGen filed a lawsuit against a parts manufacturers that is still working through the courts…