Logan county, Ohio says NO to BigWind, but it doesn’t matter…

Screen Shot 2019-02-15 at 5.57.29 PMface-1618921_640

Yesterday Jason Dagger presented Innogy’s update to the Scioto Ridge Wind Project which is sited primarily in Hardin County with a spillover of approximately 10 turbines into Logan County. This is an OPSB approved project.
 As the 2016 Examiner report explains, EverPower declared they would not build in Logan County without the PILOT.  The Logan County Commissioners responded to their constituents and denied the PILOT in June, 2016. 
Recently Innogy purchased EverPower and the decision has been made to site turbines in Logan County without the PILOT.  Mr. Dagger informed the Logan County Commissioners yesterday that the intent is to include Logan County in the Scioto Ridge footprint. 
The goal of Logan County Prosecutor Eric Stewart is to finalize a Road Use Maintenance Agreement (RUMA) with Innogy which states the conditions they must follow when using our county and township roads.  Innogy has indicated they wish to add conditions to this agreement….
 Concerned citizens have been complimented on the respect and courtesy they displayed and the intelligent and targeted questions asked of Mr. Dagger.
Mr. Dagger’s vagueness and lack of response to those questions was obvious.
Commissioner Antrim invited Mr. Dagger to begin the meeting with his presentation.  At the conclusion of that presentation, Mr. Antrim responded that though you have updated us on these changes, Logan County’s position has not changed.  We do not want you here.
County leaders are working on an agreement with a wind turbine devel-oper that will cover the costs of damage to any county or township roads.

 

Innogy SE plans to begin site preparations for Scioto Ridge Project, most of which is in southern Hardin County.

However, much of the gravel and concrete is expected to come out of Logan County and there are plans to put up around eight turbines near Belle Center.

Jason Dagger with Innogy said state regulators approved the project for 172 turbines, but the project has been scaled back to no more than

107…

He spoke Thursday before the Logan County Commissioners, Logan County Prosecutor Eric Stewart, Logan County Engineer Scott Coleman and about two dozen oppo-nents of wind turbines…

Local officials cannot stop the development nor do they have control over the project. They can, however, develop an agreement to protect the county’s investment in roads…

Dagger said the $300 million proj- ect will be completed in 2020.

This year will focus on the infrastructure and turbine site development followed by turbines going up in the spring and summer of 2020…